Project Management Professional (PMP) Exam Practice – Question1690

In the initial stage of the project life cycle, the project's technical objectives are apt to be understood only in a general sense. A major component of project conflict during this stage of the project is______________


A.
Concerns over priorities and procedures
B. Concerns about technical issues
C. Schedules
D. Confusion of establishing a project in the matrix management environment

Correct Answer: D

Explanation:

Explanation:
During project formation, there is always an element of confusion or lack of clarity regarding the balance of power between the project manager and functional managers. If not resolved, such confusion manifests itself in conflicts regarding technical decisions,
resource allocation, and scheduling later in the project.