Project Management Professional (PMP) Exam Practice – Question1691

On your project to construct a new runway for your City's airport, you are in the process of selecting vendors for various parts of this project. You have conducted your make-or-buy analysis and have issued Requests for Proposals. You believe it is important to
examine past performance of potential vendors. This means you are using______________


A.
Proposal evaluation techniques
B. Multi-disciplinary review teams
C. Analytical techniques
D. Independent estimates

Correct Answer: C

Explanation:

Explanation:
Analytical techniques are a tool and technique n conduct procurements. They are used to help organizations identify the readiness of a vendor to provide the desired end state, determine costs to support budgeting, and avoid cost overruns In evaluating past
performance they identify areas that have more risk and that may need to be monitored closely for project success.