Project Management Professional (PMP) Exam Practice – Question1693

Change control procedures, configuration management knowledge base, versions, and baselines in the develop project management plan process are:


A.
Enterprise environmental factors
B. Organizational process assets
C. Part of the project's configuration management plan, which as a subsidiary plan will be part of the project management plan
D. Part of the organization's management practices

Correct Answer: B

Explanation:

Explanation:
Organizational process assets include formal and informal plans, policies, procedures, and guidelines. As an input to the develop project management plan process, they include the items listed as well as standardized guidelines, instructions, proposal evaluation
criteria, and performance measurement criteria; project management plan template; change control procedures; project files from previous projects; and historical information and lessons learned.