Project Management Professional (PMP) Exam Practice – Question1694

You are managing a project that has five subcontractors. You must monitor contract performance, make payments, and manage provider interface. One subcontractor submitted a change request to expand the scope of its work. You decided to award a contract
modification based on a review of this request. All these activities are part of______________


A.
Control procurements
B. Conduct procurements
C. Form contract
D. Configuration management

Correct Answer: A

Explanation:

Explanation:
The purpose of control procurements is to ensure that the contractual requirements are met by the seller. This objective is accomplished by managing procurement relationships, monitoring contract performance and making changes and corrections to contracts if
appropriate.