Project Management Professional (PMP) Exam Practice – Question1695

Although the project charter serves to state the project manager's authority and responsibility on the project, the project manager further requires which type of power in order to be an effective leader?


A.
Expert
B. Legitimate
C. Position
D. Referent

Correct Answer: A

Explanation:

Explanation:
Expert power is a function of knowledge, skills, and reputation possessed by the project manager.
In such situations, project personnel will do what the project manager wants because they believe he or she knows best, and they trust and respect the project manager.