The performance measurement baseline consists of all the following EXCEPT______________


A.
Scope baseline
B. Requirements baseline
C. Schedule baseline
D. Cost baseline

Correct Answer: B

Explanation:

Explanation:
The scope, schedule, and cost baselines may be combined into a performance measurement baseline. It also may include technical and quality parameters. It then is used as an overall project baseline against which project execution is compared to measure and
manage performance. It also is used for earned value measurements.