As you manage the railroad switching station project, you are concerned that the business analyst who was responsible for preparing the WBS may have overlooked some parts of the project. In order to see if the WBS requires enhancements you decide
to______________


A.
Perform a cause-and-effect diagram
B. Meet with your sponsor
C. Use an affinity diagram
D. Review the accompanying WBS Dictionary with a member of the PMO

Correct Answer: C

Explanation:

Explanation:
In quality assurance an affinity diagram is used to generate ideas that can be linked to form organized patterns of thought about a problem. Using them in project management, one can enhance the creation of the WBS by using it to give structure to the
decomposition of scope.