Project Management Professional (PMP) Exam Practice – Question1701

If you apply the configuration management system along with change control processes project wide, you will achieve all but one of the which following objectives?


A.
Provide the basis for which the product configuration is defining
B. List the approved configuration identification
C. Document the specific responsibilities of each stakeholder in the perform integrated change control process
D. Ensure the composition of a project's configuration items is correct

Correct Answer: C

Explanation:

Explanation:
Configuration management is an integral part of the perform integrated change control process. It is necessary because projects by their nature involve changes. The integrity of baselines must be maintained by releasing only approved changes for incorporation
into the project’s products or services and by maintaining their related configuration and planning documentation.