Project Management Professional (PMP) Exam Practice – Question1702

You need to outsource the testing function of your project. Your subcontracts department informed you that the following document must be prepared before conducting the procurement:


A.
Make-or-buy analysis
B. Procurement management plan
C. Evaluation methodology
D. Contract terms and conditions

Correct Answer: B

Explanation:

Explanation:
The procurement management plan describes how the project management team will acquire goods and services from outside the performing organization. It describes how the procurement processes will be used from developing procurement documents
through closing contracts.