Project Management Professional (PMP) Exam Practice – Question1704

You are developing a project charter and want to ensure that any changes that may occur after the project begins will be controlled rigorously. You have consulted your company's configuration management knowledge base, and it contains versions and baselines
of all the following official company documents EXCEPT______________


A.
Standards
B. Strategic plans
C. Policies
D. Procedures

Correct Answer: B

Explanation:

Explanation:
The configuration management knowledge base is an organizational process asset. It contains the versions and baselines of all company policies, practices, procedures, and standards, as well as pertinent project documents.