You are developing a project charter and want to ensure that any changes that may occur after the project begins will be controlled rigorously. You have consulted your company's configuration management knowledge base, and it contains versions and baselines
of all the following official company documents EXCEPT______________
A. Standards
B. Strategic plans
C. Policies
D. Procedures
of all the following official company documents EXCEPT______________
A. Standards
B. Strategic plans
C. Policies
D. Procedures