To identify inefficient and ineffective policies, processes, and procedures in use on a project, you should conduct______________


A.
An inspection
B. A process analysis
C. Benchmarking
D. A quality audit

Correct Answer: D

Explanation:

Explanation:
A quality audit is a tool and technique for the perform quality assurance process. It is primarily used to determine whether the project team is complying with organizational and project policies, processes, and procedures.