Project Management Professional (PMP) Exam Practice – Question1708

A number of tools and techniques are helpful in the perform integrated change control process. If you want to implement an integrated change control process, you should use______________


A.
Configuration management software
B. A project management information system
C. Project status review meetings
D. Change control meetings

Correct Answer: D

Explanation:

Explanation:
Often, a project will set up a change control board, which has the responsibility for meeting and reviewing the change requests, and approving, rejecting, or other disposition of the changes. Decisions of the board are documented and communicated to
stakeholders for information and follow-up actions.