Project Management Professional (PMP) Exam Practice – Question1711

Which of the following ensures that requested changes to deliverables are thoroughly considered as part of the perform integrated change control process?


A.
Scope change control system
B. Configuration management system
C. Change control board
D. Configuration status audits

Correct Answer: B

Explanation:

Explanation:
The formal configuration management system is an important tool and technique for scope control and focuses on deliverables and documents.