Project Management Professional (PMP) Exam Practice – Question1713

All of the following statements concerning validate scope and control quality are true EXCEPT______________


A.
The processes can be performed in parallel
B. Both processes use inspection as a tool and technique
C. Validate scope is concerned with the acceptance of deliverables, and control quality is concerned with meeting quality requirements for the deliverables
D. Validate scope verification typically precedes control quality

Correct Answer: D

Explanation:

Explanation:
Validate scope focuses on accepting project deliverables, and to be accepted, they must meet the requirements. Control quality is one way to ensure that the requirements have been met, which is why control quality typically is done before validate scope.