All of the following statements concerning validate scope and control quality are true EXCEPT______________
A. The processes can be performed in parallel
B. Both processes use inspection as a tool and technique
C. Validate scope is concerned with the acceptance of deliverables, and control quality is concerned with meeting quality requirements for the deliverables
D. Validate scope verification typically precedes control quality
A. The processes can be performed in parallel
B. Both processes use inspection as a tool and technique
C. Validate scope is concerned with the acceptance of deliverables, and control quality is concerned with meeting quality requirements for the deliverables
D. Validate scope verification typically precedes control quality