The project scope baseline should be used in the identify risks process because it______________
A. Identifies project assumptions
B. Identifies all work that must be done; therefore, it includes all risks on the project
C. Helps organize all work that must be done on the project
D. Contains information on risks from prior projects
A. Identifies project assumptions
B. Identifies all work that must be done; therefore, it includes all risks on the project
C. Helps organize all work that must be done on the project
D. Contains information on risks from prior projects