Project Management Professional (PMP) Exam Practice – Question1716

The project scope baseline should be used in the identify risks process because it______________


A.
Identifies project assumptions
B. Identifies all work that must be done; therefore, it includes all risks on the project
C. Helps organize all work that must be done on the project
D. Contains information on risks from prior projects

Correct Answer: A

Explanation:

Explanation:
Project assumptions, which should be enumerated in the project scope baseline in the scope statement, are areas of uncertainty, and therefore, potential causes of project risk.