Project Management Professional (PMP) Exam Practice – Question1718

Tools and techniques used to perform quality assurance include______________


A.
Tools from control quality and plan quality management
B. Tools from performance reporting
C. Variance analysis
D. Direct and manage project execution

Correct Answer: A

Explanation:

Explanation:
The tools used from plan quality management and control quality are used in perform quality assurance. The perform quality assurance process also uses affinity diagrams, process decision program charts, interrelationship digraphs, tree diagrams, prioritization
matrices, activity network diagrams, matrix diagrams, quality audits, and process analysis.