Project Management Professional (PMP) Exam Practice – Question1719

An approach to provide insight into the health of the project and to identify any areas that require special attention is to______________


A.
Conduct periodic status reviews
B. Prepare regular status and progress reports
C. Prepare forecasts of the project's future
D. Continuously monitor the project

Correct Answer: D

Explanation:

Explanation:
The monitor and control project work process is performed throughout the project and includes collecting, measuring, and disseminating performance information and assessing measurements and trends to effect process improvement. Continuous monitoring is
important because it provides insight into the project’s health, highlighting areas requiring special attention.