Project Management Professional (PMP) Exam Practice – Question1726

Which of the following tools and techniques is used in the close project or phase process?


A.
Project management methodology
B. Work performance information
C. Expert judgment
D. Project management information system

Correct Answer: C

Explanation:

Explanation:
According to the PMBOK Guide, expert judgment is use in close project or phase to ensure closure is performed to appropriate standards.