Project Management Professional (PMP) Exam Practice – Question1727

After the project scope statement is complete, it may be necessary to update other project documents. All the following are examples of a document that may require updates EXCEPT______________


A.
Project charter

B. Stakeholder register
C. Requirements documentation
D. Requirements traceability matrix

Correct Answer: A

Explanation:

Explanation:
Outputs of the define scope project are the project scope statement and project document updates that include updates to the stakeholder register, requirements documentation, and the requirements traceability matrix.