Project Management Professional (PMP) Exam Practice – Question1729

While managing a large project in your organization, you realize that your project team requires training in contract administration because you will be awarding several major subcontracts. After you analyze your project requirements and assess the expertise of
your team members, you decide that your team will need a one-week class in contract administration. This training should______________


A.
Commence as scheduled and stated in the staffing management plan
B. Commence as scheduled and stated as part of the procurement management plan
C. Be scheduled if necessary after performance assessments are prepared and after each team member has had an opportunity to serve in the contract administrator role
D. Commence as scheduled and stated in the team development plan

Correct Answer: A

Explanation:

Explanation:
Training is a tool and technique for the develop project team process. The requirements and schedule for the develop project team process should be stated in the staffing management plan. Project team members’ skills can be developed as part of the project
activities.