Project Management Professional (PMP) Exam Practice – Question1731

Your project sponsor has asked you, "What do we now expect the total job to cost?" Given that you are using earned value, you should calculate the______________


A.
To-complete performance index
B. Estimate to complete
C. Estimate at completion
D. Budget at completion

Correct Answer: C

Explanation:

Explanation:
EAC is the total amount of money estimated to be spent on the project. It can be calculated several different ways. However, the basic approach is to add the actual costs to date plus the estimate to complete.