Project Management Professional (PMP) Exam Practice – Question1732

One key reason that the develop project charter process is so important is that it______________


A.
Documents the boundaries of the project
B. States the methods for acceptance of the project's deliverables
C. Describes the project's characteristics
D. Links the project to the ongoing work of the organization

Correct Answer: D

Explanation:

Explanation:
The project charter not only authorizes a project, it shows how the project is linked to the strategic plan of the organization. Among other things, the project charter documents the business need for the project and describes the current understanding of the
requirements.