Project Management Professional (PMP) Exam Practice – Question1734

Assume you had a phase gate meeting with your Governance Board for your project to develop the next generation radar system as part of the nation's airspace modernization program. At this meeting, the Board approved your project management plan.
However, as you begin to execute your plan, an organizational process asset to consider is______________


A.
Stakeholder risk tolerances
B. The organization's culture
C. Hiring and firing guidelines
D. Process measurement data base

Correct Answer: D

Explanation:

Explanation:

The process measurement data base is an organizational process asset that is used to collect and make available measurement data on processes and products. The other answers are examples of enterprise environmental factors used as inputs to direct and
manage the project work.