Project Management Professional (PMP) Exam Practice – Question1735

Consider the data in the table below.

Assume that your project consists only of these three activities. Your estimate at completion is $4,400.00. This means you are calculating your EAC by using which of the following formulas?


A.
EAC = AC/EV BAC
B. EAC = AC/EV [work completed and in progress] + [actual (or revised) cost of work packages that have not started]
C. EAC = [Actual to date] + [all remaining work to be done at the planned cost including remaining work in progress]
D. EAC =% complete BAC

Correct Answer: C

Explanation:

Explanation:
This formula assumes that all of the remaining work is independent of the burn rate incurred thus far. AC is $2,900 + [$500 + $1,000]. The $500 is from Activity B, and the $1,000 is from Activity C.