Your experience has taught you that inappropriate responses to cost variances can produce quality or schedule problems or unacceptable project risk. When leading a team meeting to discuss the importance of cost control, you note that cost control is concerned
with______________
with______________
A. Influencing the factors that create change to the authorized cost baseline
B. Developing an approximation of the costs of the resources needed to complete the project
C. Allocating the overall cost estimate to individual work items
D. Establishing a cost performance baseline