Project Management Professional (PMP) Exam Practice – Question1744

Each time you meet with your project sponsor, she emphasizes the need for cost control. To address her concerns, you should provide______________


A.
Work performance information
B. Cost baseline updates
C. Resource productivity analyses
D. Trend analysis statistics

Correct Answer: A

Explanation:

Explanation:
The project’s work performance information should document and communicate the CV, SV, CPI, SPI, TCPI, and VAC for the WBS components in particular for specific work packages and control accounts.