Project Management Professional (PMP) Exam Practice – Question1746

You work for an electrical utility company and will be managing a project to build a new substation that will serve a new industrial park. This project was authorized because of a______________


A.
Business need
B. Market demand
C. Technological advance
D. Customer request

Correct Answer: D

Explanation:

Explanation:
Projects can be authorized as a result of a market demand, organizational need, customer request, technological advance, legal requirement, ecological impact, or a social need. The new industrial park is an example of a project authorized because of a customer
request.