You work for an electrical utility company and will be managing a project to build a new substation that will serve a new industrial park. This project was authorized because of a______________
A. Business need
B. Market demand
C. Technological advance
D. Customer request
A. Business need
B. Market demand
C. Technological advance
D. Customer request