Project Management Professional (PMP) Exam Practice – Question1748

At the time the risk register is first prepared, it should contain all the following entries EXCEPT______________


A.
Root causes of risk
B. Structure for describing risks
C. List of risks requiring near-term responses
D. List of potential responses

Correct Answer: C

Explanation:

Explanation:
The primary outputs from identify risks are initial entries into the risk register. It ultimately contains outcomes of other risk management processes as they are conducted. As an output of identify risks, the risk register should contain a list of identified risks, a list of
potential responses, root causes that gave rise to the identified risks, and a structure for describing risks.