Project Management Professional (PMP) Exam Practice – Question1751

Project execution must be compared, and deviations must be measured for management control according to the______________


A.
Scope baseline
B. Performance measurement baseline
C. Schedule baseline
D. Control system

Correct Answer: B

Explanation:

Explanation:
The PMB is an approved, integrated scope-schedule-cost plan for the project work against which project execution is compared in order to measure and manage performance. It includes contingency reserve but not management reserve. It typically integrates
scope, schedule, and cost parameters of the project, but it may also include technical and quality parameters.