Project Management Professional (PMP) Exam Practice – Question1752

A number of items may be part of the schedule data for the project. The amount of additional detail will vary, but the data should include all the following items EXCEPT______________


A.
Schedule activities
B. Activity attributes
C. Identified assumptions
D. Resource breakdown structure

Correct Answer: D

Explanation:

Explanation:
Schedule data for the project schedule includes a number of items as it collects the information used to describe and control the schedule. It includes schedule milestones, schedule activities, activity attributes, and assumptions and constraints. It may include
resource histograms, alternate schedules, contingency reserves cash-flow projections, and order and delivery schedules.