Project Management Professional (PMP) Exam Practice – Question1755

All the following are examples of project document updates from the manage project team process EXCEPT______________


A.
Issue log
B. Roles description
C. Project staff assignments
D. Personnel skills

Correct Answer: D

Explanation:

Explanation:
Personnel skill updates are an example of an enterprise environmental factor that may require updates as a result of the manage project team process along with inputs to the organizational performance appraisals.