Project Management Professional (PMP) Exam Practice – Question1756

Recording and reporting information regarding when appropriate configuration information should be provided and regarding the status of proposed and approved changes effectively is done through______________


A.
Configuration status accounting
B. Configuration verification and audit
C. Project management methodology
D. A project management information system (PMIS)

Correct Answer: A

Explanation:

Explanation:
Configuration status accounting captures, stores, and accesses the needed configuration information to manage products and product information effectively.