The schedule management plan is a key document. It is______________
A. An output of the develop schedule process
B. A tool and technique used in the develop schedule process
C. The first time management process
D. A separate planning effort completed in conjunction with the time management processes
A. An output of the develop schedule process
B. A tool and technique used in the develop schedule process
C. The first time management process
D. A separate planning effort completed in conjunction with the time management processes