Project Management Professional (PMP) Exam Practice – Question1759

Activity attributes are used to extend the description of the activity and to identify its multiple components. In the early stages of the project, an example of an activity attribute is______________


A.
Activity codes
B. Activity description
C. Predecessor and successor activities
D. Activity name

Correct Answer: D

Explanation:

Explanation:
The components for each activity evolve over time. In the initial stages of the project, they include the activity ID, WBS ID, and the activity name. Later, additional information is added as other time management processes are performed.