Project Management Professional (PMP) Exam Practice – Question1762

Your project has a budget of $1.5 million for the first year, $3 million for the second year, $2.2 million for the third year, and $800,000 for the fourth year. Most of the project budget will be spent during______________


A.
Starting the project
B. Organizing and preparing
C. Carrying out the work
D. Closing the project

Correct Answer: C

Explanation:

Explanation:
The implementation phase (carrying out the work) is when all interfaces affecting the project must be coordinated and when the product or service of the project is created. In most projects, this phase is also where a large portion of the project budget is spent.