Project Management Professional (PMP) Exam Practice – Question1764

Typically, the seller receives formal written notice that the contract has been completed by the______________


A.
Project manager
B. Authorized procurement administrator
C. Member of the project management team responsible for daily contract administration
D. Purchasing department head

Correct Answer: B

Explanation:

Explanation:

The buyer, through its authorized procurement administrator, is responsible for providing the seller with formal written notice of contract completion. The procurement administrator does so when the seller has met all contractual requirements as articulated in the
contract. PMI,