Project Management Professional (PMP) Exam Practice – Question1765

Working in the control procurements process since your project is using five contractors, you need to update a number of organizational process assets. An example is______________


A.
Procurement management plan
B. Procurement documentation
C. Correspondence
D. Warranties

Correct Answer: C

Explanation:

Explanation:
Contract terms and conditions often require written documentation of certain aspects of buyer/seller communications. Examples include any warnings of unsatisfactory performance and requests for changes in the contract or clarification. Other organizational
process assets to update include payment schedules and requests and seller performance evaluation documentation.