Based on quality control measurements on your manufacturing project, management realizes that immediate corrective action is required to the material requirements planning (MRP) system to minimize rework. To implement the necessary changes you should
follow______________


A.
The organization's quality policy
B. The quality management plan
C. Established operational definitions and procedures
D. A defined integrated change control process

Correct Answer: D

Explanation:

Explanation:
If the recommended corrective or preventive actions or a defect repair require a change to any of the project management plans, a change request should be prepared in conformance with the perform integrated change control process.