Schedule control is one important way to avoid delays. While planning and executing schedule recovery, one tool available to you for control schedules is______________


A.
Changing the schedule management plan
B. Immediately rebase lining
C. Adjusting leads and lags
D. Changing all project and resource calendars

Correct Answer: C

Explanation:

Explanation:
Corrective action is anything that brings expected future schedule performance in line with the project plan. Adjusting leads and lags is one of many tools available to identify the cause of variation.