Project Management Professional (PMP) Exam Practice – Question1775

You have been the project manager for your nuclear submarine project for four years. While you did not assume this position until the project management plan had been prepared and approved, you find you spend a significant amount of time collecting data and
communicating. You also spend time reviewing the impact of project changes and implementing ones that have been approved. Often you have had to modify a non-conforming product, which means you are spending time on______________


A.
Corrective actions
B. Updating the project's requirements
C. Updating the traceability matrix
D. Defect repair

Correct Answer: D

Explanation:

Explanation:
Defect repair is an intentional activity to modify a nonconforming product or project component.