Assume that you are managing a project team. Your team is one in which its members confront issues rather than people, establish procedures collectively, and is team oriented. As the project manager, which of the following represents your team's stage of
development and the approach you should use during this time?
A. Storming; high directive and supportive approach
B. Norming; high directive and low supportive approach
C. Norming; high supportive and low directive approach
D. Performing; low directive and supportive approach
development and the approach you should use during this time?