Project Management Professional (PMP) Exam Practice – Question1783

You are finalizing all the contracts and ensuring that they are closed. The close procurements process involves all the following administrative actions EXCEPT______________


A.
The procurement administrator is reassigned
B. Finalizing open claims
C. Updating the project records to show the final contract results
D. Archiving the contracts and contract records for future use

Correct Answer: A

Explanation:

Explanation:
The close procurements process looks at the administration of the contract and not the people responsible or involved with the contract.