Assume you are working as the project manager on the first project in your company to use the critical chain approach to scheduling. You are a PMP and also are certified in critical chain. You are getting ready for a performance review with your Governance
Board, and you can expect they will ask questions about______________
A. The magnitude of variance against the schedule baseline
B. Schedule risk
C. Performance to date since the past review meeting
D. The buffer needed and buffer remaining
Board, and you can expect they will ask questions about______________
A. The magnitude of variance against the schedule baseline
B. Schedule risk
C. Performance to date since the past review meeting
D. The buffer needed and buffer remaining