Project Management Professional (PMP) Exam Practice – Question1791

To practice effective schedule control, your project team must be alert to any issues that may cause problems in the future. To best accomplish effective schedule control, the team should______________


A.
Review work performance information
B. Allow no changes to the schedule
C. Update the schedule management plan on a continuous basis
D. Hold status reviews

Correct Answer: A

Explanation:

Explanation:
The calculated SV and SPI time performance indicators for WBS components, in particular the work packages and control accounts, are documented and communicated to stakeholders as an output of the control schedule process.