To practice effective schedule control, your project team must be alert to any issues that may cause problems in the future. To best accomplish effective schedule control, the team should______________
A. Review work performance information
B. Allow no changes to the schedule
C. Update the schedule management plan on a continuous basis
D. Hold status reviews
A. Review work performance information
B. Allow no changes to the schedule
C. Update the schedule management plan on a continuous basis
D. Hold status reviews