Project Management Professional (PMP) Exam Practice – Question1794

A watch list of low priority risks is documented in the______________


A.
Work performance information
B. Risk register
C. Fallback plans
D. Risk response plan

Correct Answer: B

Explanation:

Explanation:
The monitor and control risks process includes keeping track of those risks on the watch list. Low-priority risks are inputs to the monitor and control risks process and are documented in the risk register. Other inputs that are part of the risk register include
identified risks and risk owners, agreed-upon risk responses, control actions to assess the effectiveness of response plans, specific implementation actions, symptoms and warning signs of risk, residual and secondary risks, and the time and cost contingency
reserves.