Project Management Professional (PMP) Exam Practice – Question1796

It often is advantageous to appoint a termination manager in the closing phase of the project and release the project manager so that he or she is available to work on another project. If this is the case, the termination manager should focus attention on all but
which one of the following?


A.
Ensuring that documentation is complete
B. Ascertaining any product support requirements
C. Receiving formal acceptance of the project from the client
D. Preparing personnel performance evaluations

Correct Answer: D

Explanation:

Explanation:
The project manager, or whoever supervised the work of each individual team member, should prepare the personnel evaluations because they have an intimate understanding of the work performed by the team members. The termination manager focuses
instead on the administrative requirements of termination and the environment within which the project will be operating if it is continued in any way.