It often is advantageous to appoint a termination manager in the closing phase of the project and release the project manager so that he or she is available to work on another project. If this is the case, the termination manager should focus attention on all but
which one of the following?
A. Ensuring that documentation is complete
B. Ascertaining any product support requirements
C. Receiving formal acceptance of the project from the client
D. Preparing personnel performance evaluations