Project Management Professional (PMP) Exam Practice – Question1801

Life-cycle phase definitions are different in different industries. For example, all of the following are terms that could be used in the closing phase of a project EXCEPT______________


A.
Testing and commissioning
B. Conversion
C. Implementation
D. Final audit

Correct Answer: C

Explanation:

Explanation:
Regardless of the many terms used across many industries, implementation would be considered a term used in the executing phase in which the work is carried out and done. Kerzner 2009, 69