Project Management Professional (PMP) Exam Practice – Question1802

Your company is embarking on a project to launch a new product delivery service. You are the project manager for this project and have just finished the concept phase. The various outputs/deliverable(s) for this phase include______________


A.
Project management plan

B. Scope of work and requirements
C. Project charter and stakeholder register
D. Roles and responsibilities of the project manager

Correct Answer: C

Explanation:

Explanation:
The project charter signifies official sanction by top management and starts the planning, or development, phase. This document formally recognizes the existence of the project and provides the project manager with the authority to apply organizational resources
to project activities. The stakeholder register is an output of identify stakeholders and also an output during the initiating processes.