Because risk management is relatively new on projects in your company, you decide to examine and document the effectiveness of risk responses in dealing with identified risks and their root causes. You therefore______________


A.
Conduct a risk audit
B. Hold a risk status meeting
C. Ensure that risk is an agenda item at regularly scheduled staff meetings
D. Reassess identified risks on a periodic basis

Correct Answer: A

Explanation:

Explanation:
The risk audit is a tool and technique in the control risks process with two purposes: to assess the effectiveness of risk responses and to evaluate the effectiveness of the risk management process.